A house is going up here: a TR3M in six days
- 3
- Modules, all set on day one
- about 2 hrs
- per module for lifting and positioning
- 6 days
- on site, from setting up to cleaning
A house from the factory doesn’t put itself up. Before you can move in, it is set down on your plot, joined, connected and finished off at the points where the modules meet. What that looks like in practice is shown by our assembly team’s daily reports from a TR3M that was set up in November. Three modules, six days of on-site assembly, mostly seven people, starting at eight every morning.
Day 1: three modules in one day
The first day starts with preparation. Two people unpack the first module, fit the lifting beam and attach it to the crane beam, which takes about 40 minutes. At the same time, three colleagues set the lifting rods according to the drawing, also in about 40 minutes. Two more spend an hour marking out the axes along which the modules are aligned on the ground screws.
Then the lifting begins. On average it took about two hours per module, from setting up the lifting system to lifting and precise positioning. As soon as a module was in place, the team split up: three prepared the lifting system for the next module, four fixed the module they had just set onto the ground screws. And so it went, three times.

Knocking off at half past seven. By the evening, all three modules were standing.
The roof sheeting couldn't be fitted that day. So the team secured the structure and fixed a protective membrane in place to keep any water out.
Day 2: three modules become one house
Now it’s all about the joints, the places where the modules meet. The team fits the connecting bolts between the modules, applies sealing tape on the inside and closes the walls at the joints with plasterboard, outside and in. The ceiling follows later.
Under the house, the trench for water and electricity is widened, then the house is connected to the water supply and the sewer. That took longer than planned: there was little room to work between the ground and the house. Outside, the electrical connections between the modules are laid; inside, work begins on the final cable connections in the junction boxes.
The spot for the heat pump’s outdoor unit is also fixed on this day. Digging for it starts by hand and has to be interrupted. That’s part of a building site too.

Day 3: power and facade
The cables are connected and pulled from outside into the plant room, with sealing sleeves at the wall penetrations. The connections in the junction boxes between the modules are finished. Twelve outdoor lights and the outdoor sockets are also fitted.
On the outer shell, sealing tape is applied to the vapour-permeable membrane. Then the facade is closed at the module joints with timber cladding, and the roof sheeting is fitted at the module joints and around the lifting rods.

Twelve lights, one facade: facade and roof sheeting are fitted at the joints.
Day 4: smoothing inside, closing the floor
A shorter day, knocking off at 4 pm. Plasterboard goes onto the ceiling, and the joints are filled, with a second coat where needed. On a test area, the team tries out the decorative plaster to see how the joint will look later. On the floor, OSB boards are laid and screed is poured where the modules meet.
Outside, the plugs are set into the timber profiles of the facade and painted. The house gets temporary site power, and the lighting is prepared for testing. And the excavation for the heat pump is finished: gravel layer, foundation and metal bracket are in place.
Day 5: the heat pump arrives
The heat pump’s outdoor unit is set on its foundation and bracket, the flow and return are connected, then the power. In the distribution board, the team installs a type B residual current device for the heat pump. Inside, the surfaces are prepared for painting, the windows protected with film and the frames masked off.
Day 6: paint, water, testing, cleaning
On the final day, the decorative plaster is touched up and the interior painted. One ceiling in the second bedroom is left for now, because the last plaster correction needs to dry first. The underfloor heating pipes are connected, and the heating circuits and manifold are filled with water, but not the rest of the system yet. The heat pump pipes are insulated and the outdoor circuits electrically tested. Finally, the roof sheeting is cleaned of assembly dirt and the facade is washed.
What we take away from it
Six days of on-site assembly, and not everything went to plan: the sewer connection took longer, the digging had to pause, one ceiling is still waiting to be painted. That’s building. But on the first evening all three modules were standing, and after six days, three parts had become one house.
By the way, for on-site assembly we quote about a week as a figure based on experience, not a promise. Every site is different, and this report shows why: the terrain, the ground, the connections.
To see what a finished TR3M looks like inside, visit the show house in Bad Vilbel.
Source
- Daily reports from the DWELLII assembly team, 19 to 24 November 2026 (internal source, project channel). The customer’s name and location are not given, to protect the building owners.