From the building site 5 min read

A house is going up here: a TR3M in six days

Three modules in one day, then five days of joining, connecting and fitting out. Our assembly team noted down day by day what got done and what didn't.

TR3M modular house on a building site after assembly: grey and light-brown timber facade, red front door still in protective film, the house standing on ground screws
A TR3M after assembly, still in the middle of the building site
3
Modules, all set on day one
about 2 hrs
per module for lifting and positioning
6 days
on site, from setting up to cleaning

A house from the factory doesn’t put itself up. Before you can move in, it is set down on your plot, joined, connected and finished off at the points where the modules meet. What that looks like in practice is shown by our assembly team’s daily reports from a TR3M that was set up in November. Three modules, six days of on-site assembly, mostly seven people, starting at eight every morning.

Day 1: three modules in one day

The first day starts with preparation. Two people unpack the first module, fit the lifting beam and attach it to the crane beam, which takes about 40 minutes. At the same time, three colleagues set the lifting rods according to the drawing, also in about 40 minutes. Two more spend an hour marking out the axes along which the modules are aligned on the ground screws.

Then the lifting begins. On average it took about two hours per module, from setting up the lifting system to lifting and precise positioning. As soon as a module was in place, the team split up: three prepared the lifting system for the next module, four fixed the module they had just set onto the ground screws. And so it went, three times.

The TR3M standing on the plot, surrounded by heaped-up earth, boards and sheeting
The TR3M after being set up

Knocking off at half past seven. By the evening, all three modules were standing.

The roof sheeting couldn't be fitted that day. So the team secured the structure and fixed a protective membrane in place to keep any water out.

Day 2: three modules become one house

Now it’s all about the joints, the places where the modules meet. The team fits the connecting bolts between the modules, applies sealing tape on the inside and closes the walls at the joints with plasterboard, outside and in. The ceiling follows later.

Under the house, the trench for water and electricity is widened, then the house is connected to the water supply and the sewer. That took longer than planned: there was little room to work between the ground and the house. Outside, the electrical connections between the modules are laid; inside, work begins on the final cable connections in the junction boxes.

The spot for the heat pump’s outdoor unit is also fixed on this day. Digging for it starts by hand and has to be interrupted. That’s part of a building site too.

Building site in front of the TR3M with a ladder, scaffolding parts, pallets and a yellow cable on the ground
Everyday life on site: ladders, scaffolding parts, cables

Day 3: power and facade

The cables are connected and pulled from outside into the plant room, with sealing sleeves at the wall penetrations. The connections in the junction boxes between the modules are finished. Twelve outdoor lights and the outdoor sockets are also fitted.

On the outer shell, sealing tape is applied to the vapour-permeable membrane. Then the facade is closed at the module joints with timber cladding, and the roof sheeting is fitted at the module joints and around the lifting rods.

Side view of the TR3M with wall lights switched on against the timber facade
The outdoor lights are in place

Twelve lights, one facade: facade and roof sheeting are fitted at the joints.

Day 4: smoothing inside, closing the floor

A shorter day, knocking off at 4 pm. Plasterboard goes onto the ceiling, and the joints are filled, with a second coat where needed. On a test area, the team tries out the decorative plaster to see how the joint will look later. On the floor, OSB boards are laid and screed is poured where the modules meet.

Outside, the plugs are set into the timber profiles of the facade and painted. The house gets temporary site power, and the lighting is prepared for testing. And the excavation for the heat pump is finished: gravel layer, foundation and metal bracket are in place.

Day 5: the heat pump arrives

The heat pump’s outdoor unit is set on its foundation and bracket, the flow and return are connected, then the power. In the distribution board, the team installs a type B residual current device for the heat pump. Inside, the surfaces are prepared for painting, the windows protected with film and the frames masked off.

Day 6: paint, water, testing, cleaning

On the final day, the decorative plaster is touched up and the interior painted. One ceiling in the second bedroom is left for now, because the last plaster correction needs to dry first. The underfloor heating pipes are connected, and the heating circuits and manifold are filled with water, but not the rest of the system yet. The heat pump pipes are insulated and the outdoor circuits electrically tested. Finally, the roof sheeting is cleaned of assembly dirt and the facade is washed.

What we take away from it

Six days of on-site assembly, and not everything went to plan: the sewer connection took longer, the digging had to pause, one ceiling is still waiting to be painted. That’s building. But on the first evening all three modules were standing, and after six days, three parts had become one house.

By the way, for on-site assembly we quote about a week as a figure based on experience, not a promise. Every site is different, and this report shows why: the terrain, the ground, the connections.

To see what a finished TR3M looks like inside, visit the show house in Bad Vilbel.

Source

  • Daily reports from the DWELLII assembly team, 19 to 24 November 2026 (internal source, project channel). The customer’s name and location are not given, to protect the building owners.

02Show house

Fancy seeing it for yourself?

The TR3M show house is in Bad Vilbel, open Wednesday to Sunday from 11 am to 6 pm. Drop in without booking, or register in advance and get free entry to the show house park.

03Magazine

Also worth a read

  • TR3M show house on a single level: timber façade, large windows and a wooden terrace in front

    Bungalow & living in later life

    Bungalow or two storeys: what really matters as you age

    Eight in ten households with people aged 65+ have no step-free access to their own home. Why the question of stairs comes up sooner than many people think.

    4 min read

  • Living and dining area in the TR3M show house with wooden table, armchairs and large windows onto the terrace

    Fittings & makers

    Advertisement Advertisement: DWELLII is a sales partner of Ethnicraft

    Furniture made to stay: a portrait of Ethnicraft

    A house only becomes a home when the furniture is right. Ethnicraft from Belgium makes solid wood furniture, and you can order it together with your DWELLII house.

    4 min read

All articles in the Magazine